wendyjoy wrote:Casa del Mar Beach Resort
Phase 1&Phase 2Bathrooms
Renovation schedule
as of December 4, 2025
Suite stack Start week End week
Phase 1 Completed
1109 – 1509 Completed
1111 – 1511 Completed
1113 – 1513 Completed
1115 – 1515 Completed
1117 – 1517 Completed
1119 – 1519 Completed
1121 – 1521 Completed
1114 – 1514 Completed
1116 – 1516 Completed
1118 – 1518 41 49 – 2025
1120 – 1520 13 20 – 2026
1122 – 1522 17 24
1123 – 1523 21 28
1124 – 1524 25 32
1125 – 1525 29 36
Note: This schedule is subject to change
Hopefully this helps.